Assumed within the core range; exact dosing and control must still be specified.
Assumed within the core plant range.
No separate feature pump, tank, waterproofing or controls are added.
The approved safety walkway and drainage still need a separate written scope.
Use the approved drawing area, not the pool-water footprint.
The result excludes the barrier price, but the approved pool-safety design still controls.
Use the approved barrier line, including the gate position—not the pool perimeter by assumption.
No cover pit, track, reel or electrical provision is added.
Indicative project planning range
AED 128,000–270,000
For a 8 × 4 m concrete skimmer pool with the selected site, finish and optional scope.
Budget component
Planning range
Core shell, waterproofing, basic MEP and plant
AED 120,000–230,000
Access and ground-risk allowance
AED 0–15,000
Consultant, NOC and authority planning allowance
AED 8,000–25,000
Ground, groundwater, retaining and buried-service assumptions need written confirmation.
The required approved pool barrier is excluded from this estimate and must remain in another written scope.
Planning range only—not a quote, engineering design or Bestimate transaction average. It excludes unselected landscaping, utility diversion, retaining work, unusual dewatering, temporary works, community deposits and product upgrades not listed above.